Starting in 2010, the Clean Water Facility project team has been working with City Council and the public. See below for Council presentations, project updates, public meeting materials, and project planning documents. Click here to view past project announcements and construction updates.
2019
City Council Agenda Bills
No 2019 agenda bills at this time. More to come soon.
City Council Updates and Presentations
June 19 - Update to City Council on project schedule, construction activities, and Windjammer Park Grand Opening
Update
June 4 - Council recognition of the Splash Park Naming Contest winner and approval of new Splash Park name
Update
May 22 - Council vote to determine the winner of the Splash Park Naming Contest and update to Council on project schedule and construction activities
Update
May 7 - Update to City Council on US Navy wastewater treatment plant connect and treatment rate analysis
Update
April 16 - Update to City Council on project schedule and construction activities
Update
March 27 - Update at City Council workshop on Windjammer splash park grand opening event and naming contest
Update
March 19 - Update to City Council on project schedule and construction activities
Update
Video
March 5 - City Council approval of Puget Sound Energy’s electrical easement to provide power service to Windjammer Park.
Update
February 19 - Update to City Council on project schedule and construction activities
Update
Video
January 15 - Update to City Council on project schedule and construction activities
Update
Video
January 2 - Update to City Council on rate analysis to connect US Navy facilities to the Clean Water Facility
Update
Project Updates
June 20: Newsletter distributed to Oak Harbor residents included an announcement about the splash park naming contest winner, information about the Grand Opening of Windjammer Park, a look at Windjammer Park through the years, and information and fun facts about new park elements.
Newsletter
2018
City Council Agenda Bills
November 20 – Authorizing a budget amendment, including for the Clean Water Facility and Windjammer Park
Agenda bill
September 18 – Clean Water Facility – Authorizing Reimbursement from the General Fund to the Clean Water Facility
Agenda bill
Video
August 21 – Clean Water Facility – Professional Services Agreement Amendment No. 10: ERCI - Archaeology Services for Clean Water Facility and Windjammer Park
Agenda bill
August 21 – Clean Water Facility – Professional Services Agreement Amendment No. 3: KBA Construction, Inc
Agenda bill
August 21 – Authorization to Submit Rate Analysis Proposal to Navy for Wastewater Treatment Plant, connection and wastewater treatment
Agenda bill
April 17 - Clean Water Facility – Guaranteed Maximum Price amendment number 13
Agenda bill
January 2 - Clean Water Facility - General Contractor/Construction Manager Partial release of Retainage
Agenda bill
City Council Updates and Presentations
December 18 - Update to City Council on project schedule, ribbon cutting ceremony for the Clean Water Facility and construction activities
Update
Video
November 20 – Update to City Council on project schedule and construction activities
Update
Video
November 7 – Update at City Council workshop on project schedule and construction activities
Update
Video
October 16 – Update to City Council on project schedule and construction activities
Update
Video
October 2 – Update to City Council on project schedule and construction activities
Update
Video
September 18 – Update to City Council on project schedule and construction activities
Update
Video
September 4 – Update at City Council workshop on project schedule and construction activities
Update
Video
August 22 – Update at City Council workshop on optional consultant services, the biosolid storage facility and the biosolids beneficial use services agreement at the Boulder Park Project
Update
Video
August 21 – Update to City Council on project schedule and construction activities
Update
Video
August 8 – Update to City Council on project schedule and construction activities
Update
Video
July 25 – Update at City Council workshop on funding options for Windjammer Park pavilion and west kitchen, consultant contract amendments and next steps for the windmill
Update
Video
June 5 – Update at City Council on project schedule and construction activities
Update
Video
May 23 – Update at City Council Workshop on RV Dump Station closure and discussion of future plans
Update
Video
May 23 – Update at City Council Workshop on general contractor construction management contract organization and contingency process
Update
Video
May 15 – Update to City Council on project schedule and construction activities
Update
Video
May 1 – Update to City Council on project schedule and construction activities
Update
Video
April 17 – Update to City Council on project schedule, construction activities and GMP #13
Update
Video 1
Video 2
April 11 – Update to City Council on cost of the clean water facility and Windjammer Park improvements.
Video
Presentation (below)
April 3 – Update to City Council on project schedule and construction activities
Update
Video
March 20 – Update to City Council on project schedule and construction activities
Update with monthly report
Video
March 5 – Update at City Council Workshop on project cost and Windjammer Park.
Video
Presentation (below)
February 20 - Update to City Council on project schedule and construction activities.
Update
Video
February 15 - Update at City Council Workshop on project cost.
Video
February 6 - Update to City Council on construction progress, funding, and schedule.
Update
Video
January 16 - Update to City Council on work packages, construction progress, and schedule.
Update
Video
January 2 - Update to City Council on project schedule and construction activities
Update
Video
Project Updates
November 29: Ribbon cutting ceremony for the Clean Water Facility included speeches from project partners and banners displayed in the administration building.
Video
Displays
June 7: Newsletter distributed to Oak Harbor residents included an update on the clean water facility and look at the year ahead, rate information, and a Windjammer Park improvements update.
Newsletter
April 30: Postcard distributed to Oak Harbor residents included an announcement about the closure of large portions of Windjammer Park for construction on new park elements.
Postcard
2017
City Council Agenda Bills
October 17 - Professional Services Agreement: ERCI for the Wastewater Treatment Plant - Amendment No. 9
Agenda bill
Video
October 3 - Consultant Agreement - Carollo Engineers for Effluent Reuse, CWF- Amendment No. 18
Agenda bill
Video
August 2 - Agenda Bill 4.e: Clean Water Facility - Carollo Engineers - Consultant Agreement Amendment No. 17 for implementation of an asset management system
Agenda bill
April 18 - Resolution 17-08: Clean Water Facility - Adopting the 30% Phase 1 Windjammer Park Design Documents
Agenda bill
Video
April 4 - Professional Services Agreement: HDR, Inc. - Utility Rate and Fee Update
Agenda bill
Video
March 21 - Clean Water Facility - General Contractor/Construction Manager GMP Amendment #12
Agenda bill
Video
March 7 - Clean Water Facility - Puget Sound Energy Commercial Line Extension Agreement
Agenda bill
February 21 - Wastewater Treatment Plant - Professional Services Agreement with ERCI - Amendment No. 8
Agenda bill
Video
January 17 - Clean Water Facility - General Contractor/Construction Manager GMP Amendment #11
Agenda bill
Video
City Council Updates and Presentations
December 5 - Update to City Council on construction progress, Windjammer Park updated design, and equipment delivery
Update
Video
November 21 - Update to City Council on project efficiencies, such as building information models, and bid packages
Update
Video
November 8 - Update to City Council on Lagoon Facility transfer, Windjammer Park design progress, and construction progress
Update
Video
October 17 - Update to City Council on building appearance, construction progress, and schedule
Update
Video
October 3 - Update to City Council on construction progress, contracts, and schedule
Update
Video
September 19 - Update to City Council on construction progress
Video
September 5 - Update to City Council on recent Windjammer Park outreach and construction progress
Update
Video
August 15 - Update to City Council on construction progress
Update
Video
August 2 - Updated to City Council on Windjammer Park Phase 1 - 60% design update
Update
Video
Presentation (below)
August 2 - Update to City Council on construction progress and schedule
Update
Video
July 5 - Update to City Council on equipment delivery, facility software, and Windjammer Park Phase 1 design progress.
Update
Video
June 6 - Update to City Council on construction progress, Family Fun Day, security software development, and Art Commission coordination
Update
Video
May 16 - Update to City Council on Windjammer Park Phase 1 design, construction activities, and Art Commission coordination
Update
Video
May 2 - Update to City Council on construction site and office access, recent construction activities, and overall schedule
Update
Video
April 18 - Update to City Council on construction progress
Update
Video
April 4 - Update to City Council on project progress
Update
Video
March 22 - Presentation at City Council Workshop on Windjammer Park 30% design progress
Video
Presentation (below)
March 21 - Update to City Council on recent project milestones and construction activities
Update
Video
March 7 - Update to City Council meeting on recent project progress
Update
Video
February 22 - Presentation at City Council workshop on the future interpretive center
Video
February 22 - Presentation at City Council workshop on archaeology
Video
February 21 - Update at City Council meeting on recent project milestones
Update
Video
February 7 - Update at City Council meeting on recent construction activities and funding.
Update
Video
January 17 - Update at City Council meeting on recent activities, including the Windjammer Park design open house, construction activities, and funding for Windjammer Park.
Update
Video
January 3 - Update at City Council meeting on current construction activities.
Update
Video
2016
Highlights: February 4 and March 29 public and community advisory group meetings regarding the Windjammer Integration Plan, May 5 City Council adoption of final facility design, May 25 City Council adoption of Windjammer Park Integration Plan.
City Council Agenda Bills
November 15 - Amendment to WQC-2016-OakHar-00240 - SRF Loan Financing
Agenda bill
November 15 - Clean Water Facility - Carollo Engineers - Consultant Agreement Amendment No. 16 for Windjammer Park Improvements
Agenda bill
Video
November 15 - Clean Water Facility - General Contractor/Construction Manager GMP #10
Agenda bill
Video
October 4 - Clean Water Facility - GMP No. 9 with Hoffman Construction for Electrical and Mechanical Services
Agenda bill
Video
September 6 - ERCI - Consultant Agreement Amendment No. 7 for Professional Services
Agenda bill
Video
September 6 - Carollo Engineers - Consultant Agreement Amendment No. 15 for Interpretive Center Design
Agenda bill
Video
September 6 - Clean Water Facility - General Contractor/Construction Manager GMP Amendment # 8
Agenda bill
Video
June 7 – Resolution 16-15: Windjammer Park Integration Plan
Resolution
Video
May 3 – Carollo Engineers – Consultant Agreement Amendment No. 14 for Services During Construction
Agenda bill
Video
May 3 – KBA, Inc – Contract Amendment No. 2 for Construction Management Services
Agenda bill
Video
April 27 – 16-005-Carollo Engineers – Amendment No 14 to the PSA for Services during Construction of the Clean Water Facility
Video
April 27 – 16-006 KBA Inc – Amendment No 2 to the PSA for Construction Management of the Clean Water Facility
Video
April 5 – Clean Water Facility – General Contractor/Construction Manager GMP Amendment #7
Agenda bill
Video
Presentation (below)
March 15 – Ordinance No. 1760: 2017 – 2018 Wastewater Rates
Agenda bill
Video
March 1 – Ordinance No. 1756: Issuance of Waterworks Utility Bonds
Agenda bill
Video
March 1 – Discussion of Property Acquisition regarding Wells Fargo
Video
February 16 – C/A 4.j – Clean Water Facility – Puget Sound Energy Schedule 74 Agreement and Temporary Service Agreement to Underground Power Lines
Agenda bill
February 10 – Discussion and Possible Action on Clean Water Facility Room
Agenda bill
Video
February 2 – Clean Water Facility – Carollo Engineers – Consultant Agreement Amendment No. 13 for SCADA Services
Agenda bill
Video
January 19 – Clean Water Facility – General Contractor/Construction Manager GMP Amendment #6
Agenda bill
January 12 – Resolution 16-02: 2016 Legislative Priorities
Agenda bill
January 5 – C/A 4.e – Perkins Coie, LLP Engagement Letter – Legal Counsel for the Clean Water Facility
Agenda bill
City Council Updates and Presentations
December 6 - Update at City Council meeting on current construction activities.
Update
Video
November 15 - Update at City Council meeting on funding and current and future construction activities.
Update
Video
November 1 - Update at City Council meeting on construction progress and phasing.
Update
Video
October 26 - Update at City Council workshop on State Revolving Fund (SRF) loan application.
Update
Video
October 18 - Update at City Council meeting on design progress and recent activities.
Update
Video
October 4 - Update at City Council meeting on construction progress and funding.
Update
Video
September 27 - Update at City Council Workshop on cost, schedule, and funding.
Video: Project Review
Video: Total project cost definitions and discussion
Video: Project funding strategy
Video: Rate review
Presentation (below)
September 6 - Update on project schedule and recent and upcoming construction activities
Update
Video
August 24 - Update at City Council Workshop on GMP No. 8 (Hoffman Construction – Concrete Self-Performance No. 2)
Video
August 24 - Update at City Council Workshop on ERCI Amendment No. 7
Video
August 24 - Update at City Council Workshop on Carollo Engineering Amendment No. 15
Video
August 3 - Update on costs, contracts, and construction progress
Update
Video
July 5 - Update on construction activities, including completed excavation and micropile installation
Update
Video
June 7 – Update on construction progress, Family Fun Day, and Oak Harbor High School Art Club stormwater treatment tank art installation
Update
Video
May 25 – Update on the Windjammer Park Integration Plan and presentation of proposed concept
Video
Presentation (below)
May 17 – Update on recent and upcoming Clean Water Facility construction activities, stormwater treatment tank painting and Family Fun Day
Update
Video
May 5 – Update on Clean Water Facility design at City Council workshop
Presentation (below)
May 3 – Update on recent Clean Water Facility construction activities, schedule and upcoming events
Update
Video
April 27 – Update on Windjammer Park Integration Plan
Video
April 19 – Update on recent construction, Windjammer Park Integration Plan milestones, and contractor outreach efforts
Update
Video
April 5 – Update on recent construction activities, the Windjammer Park Integration Plan, contractor outreach, and upcoming design milestones
Update
Video
March 23 – Update at City Council Workshop on GMP 8 (Hoffman Concrete Services)
Video
March 15 – Update on construction milestones, existing plant repairs, contractor outreach, and the Windjammer Park Integration Plan
Update
Video
March 1 – Update on construction activities, funding sources, contractor outreach, and the Windjammer Park Integration Plan
Update
Video
February 16 – Update on design progress and construction activities
Update
Video
February 2 – Update on construction progress, the Windjammer Park Integration Plan, and funding
Update
Video
January 19 – Update discussed project progress, including permit applications and the next phase of construction
Update
January 5 – Update shared progress on stone column work, project work with local contractors, and a general project update
Video
Update
Public Meetings
Project Updates
November 7: Newsletter distributed to Oak Harbor residents included a review of one year in construction, rate information, and a Windjammer Park planning update.
Newsletter
July 28: Newsletter distributed to Oak Harbor residents included final facility design renderings, a look at the Windjammer Park Integration Plan, and community involvement highlights.
Newsletter
January 28 – Construction update flier with information on sheet pile installation
Flier
2015
Highlights: May 6 design workshop and August 12 design open house collected input and feedback on the architectural “look and feel” of the new facility. A December 3 newsletter commemorated the Clean Water Facility groundbreaking and informed Oak Harbor about facility construction.
City Council Agenda Bills
December 15 – Agenda Bill no. C/A 4.k: Clean Water Facility – Hoffman GMP No. 4, Change Order No. 1 – Increase the size and pre-drill the Sheet Piles for the Project
Agenda bill
Video
December 15 – Resolution 15-34: Inclusion of a Community Use Room into the Construction of the Clean Water Facility
Agenda bill
Video
Presentation (below)
December 15 – Resolution 15-42: Change in Property Disposition for the Clean Water Facility
Agenda bill
Video
October 20 – Resolution 15-33: Clean Water Facility – Bio-solids Handling
Agenda bill
Video
October 20 – Resolution 15-34: Clean Water Facility – Addressing the inclusion of a community use room into the construction of the Clean Water Facility
Agenda bill
Video
October 20 – Clean Water Facility – General Contractor/Construction Manager GMP Amendment #4
Agenda bill
Video
October 20 – Clean Water Facility – General Contractor/Construction Manager GMP Amendment #5
Agenda bill
Video
October 20 – Clean Water Facility – Carollo Engineers – Consultant Agreement Amendment No. 12
Agenda bill
Video
October 20 – Clean Water Facility – KBA, Inc. Contract Amendment No. 1 for Construction Management Services
Agenda bill
Video
October 20 – Clean Water Facility – Professional Services Agreement with ERCI – Amendment No. 6
Agenda bill
Video
September 15 – Authorizing the Mayor, or designee, to sign the 2017 Clean Water State Revolving Fund (CWSRF) funding application
Agenda bill
September 1 – Adopting an Architectural Concept for the Clean Water Facility
Agenda Bill (Resolution 15-27)
Video
September 1 – Adopting the Good Neighbor Plan for the Construction of the Clean Water Facility
Agenda Bill (Resolution 15-28 – Includes Good Neighbor Plan Document)
Video
September 1 – Contract for Advisory Services- Katy Isaksen & Associates
Agenda Bill
Contract
Video
July 7 – Delay the Closing Date of the Staysail RV Park
Agenda Bill (Resolution 15-22)
July 7 – Staysail RV Park/Windjammer Park Lease Agreement
Agenda Bill (Resolution 15-24)
July 7 – Temporary Construction Easement and Agreement between the general fund and the sewer fund
Agenda Bill
July 7 – Wells Fargo Possession and Use Agreement
Agenda Bill
July 7 – Ordinance 1738, Wells Fargo Condemnation
Agenda Bill
Video
July 7 – Notice to Proceed with Schedule 74 Design with Puget Sound Energy (PSE) (undergrounding power lines along City Beach Street)
Agenda Bill
Video
July 7 – Beach View Relinquishment of Easements and Substitute Parking Agreement
Agenda Bill
Video
June 16 – Increased contract amounts with Hoffman Construction and Equinox Research Consulting International (ERCI)
Agenda Bill (Hoffman)
Agenda Bill (ERCI)
March 3 – Solicit Construction Management Services
Agenda Bill
Video
February 3 – Increased Contract Amounts with Equinox Research Consulting International (ERCI) and Perkins Coie
Agenda Bill (Perkins Coie)
Agenda Bill (ERCI)
January 6 – Defined Construction Work Area, Temporary Closure of Staysail RV Park
Agenda Bill (Resolution 14-43 – Defining Work Area)
Video
City Council Updates and Presentations
December 16 – City Council Workshop discussed the Windjammer Park Integration Plan.
Summary
Video
Presentation (below)
December 15 – Update included information on site preparation, facility construction, and funding.
Update
December 1 – Update included information on recent milestones, upcoming activities, preparation for facility construction, funding and cost.
Update
Video
November 18 – City Council Workshop discussed a high level overview of the process that will be used to develop the Windjammer Park Integration Plan.
Video
November 17 – Update included information on preparation for facility construction, design progress regarding the potential community room, funding and cost.
Update
Video
November 4 – Update included information on outfall construction completion, design progress, cost, funding and the upcoming groundbreaking event.
Update
Video
October 28 – City Council Workshop debuted the proposal to create a Windjammer Park Integration Plan, which will develop a long-term plan for the park.
Video
October 20 – Update included information on construction, design progress, cost and funding.
Update
Video
October 6 – Update included information on cost estimates, funding, and future construction activities.
Update
Video
September 30 – Special City Council Workshop included presentations on the 60 percent cost estimate, project finance, and a rates impact study.
Video
Presentation (Cost Estimate)
Presentation (Finance)
Presentation (Rate Study)
September 23 – Workshop included a presentation with a high level overview of the 60 percent design and cost estimates.
Handout
Video
Presentation (below)
September 15 – Update included information on outfall construction progress, planning, and funding.
Update
Video
September 1 – Update included information on recently completed and upcoming work, permitting, and funding.
Update
Video
August 26 – Workshop included a schedule for the partial closing the overflow camping area.
Video
August 26 – Workshop included a presentation of the Good Neighbor Plan for Clean Water Facility construction.
Update
Video
Good Neighbor Plan (Handout)
August 26 – Workshop included an overview of the Design Concept Open House.
Summary of Clean Water Facility Open House
Update
Video (open house)
Video (architectural concept)
Presentation (below)
August 5 – Update included information on 60% design, the August 12 Open House, and early site exploration results.
Update
Video
July 22 – Workshop included information on the Wastewater Treatment Facility boundary line adjustment.
Update
Video
July 22 – Workshop included an introduction and overview of the Communication and Good Neighbor Plan.
Update
Video
Presentation (below)
July 7 – Update included funding sources and a biosolids dryer cost estimate.
Update
Video
June 17 – Workshop included a walk of the future facility location, information on the technical needs of the facility, and an update on the design workshops.
Handout
Presentation (below)
June 16 – Update included information on notifications, permitting, site preparation, and cost estimates.
Update
Video
April 7 – Update included information on facilities plan, RV park closures, and sewer rates for residents.
Video
Presentation (below)
March 17 – Update included information on permitting, cost estimates and funding, and design.
Update
Video
Design Workshops
May 6 – Second design workshop collecting input on the architectural “look and feel” of the new facility.
Boards
High-level summary
Presentation (below)
Public Meetings
August 13–21 – Design Online Open House public feedback on facility design concepts.
Online open house (PDF)
August 12 – Design Open House gathered feedback from the public on facility design concepts.
Boards
Summary
Presentation (below)
Project Updates
December 17 – Construction update flier with information on stone column installation.
Flier
December 3 – Newsletter distributed to Oak Harbor residents included a cost update, information on facility construction, an updated schedule and information about the Windjammer Park Integration Plan.
Newsletter
August 14 – City Updates with Kellye Mazzoli – City Engineer Joe Stowell talked about the design of the facility and the technology involved in cleaning wastewater.
Video
June 19 – Newsletter distributed to Oak Harbor residents included a project overview, information on outfall construction, and a project schedule update.
Newsletter
June 12 – City Updates with Mayor Scott Dudley – Project staff talked about outfall construction near Oak Harbor Bay in Windjammer Park with Mayor Scott Dudley.
Video
2014
Highlights: November 13 design workshop collected input on the architectural "look and feel" of the facility; April 16 public meeting provided the community with a general project update.
City Council Agenda Bills
Design Workshops
November 13 – First design workshop collecting input on the architectural “look and feel” of the new facility.
Full summary
Public Meetings
April 16 – Update included information on siting factors, selection of a General Contractor/Construction Manager (GC/CM) firm to build the facility, and future opportunities for public involvement.
Presentation (below)
Project Updates
June – Update included selection of a General Contractor/Construction Manager (GC/CM) for the project.
Project Update
February – Update included site selection and Windjammer Park field work.
Project Update
2013
Highlights: March 6 public meeting included an update on rate information; the facilities plan was published for public review.
City Council Agenda Bills
December 17 –General Contractor/Construction Manager (GC/CM) Advisor Agreement with Olympic Associates Company (OAC)
Agenda Bill
December 17 – Modified Municipal Code to allow for GC/CM
Agenda Bill
December 3 – Directed Staff to Pursue GC/CM
Agenda Bill (Resolution 13-32)
Video
December 3 – Adopted Facility Plan
Agenda Bill (Resolution 13-31)
Video
August 7 – Approval of Professional Services Agreement with Robinson, Stafford & Rude, Inc. (RSRI) for Value Engineering Services related to Wastewater Treatment Plant
Agenda Bill
Video
May 7 – Approval of Professional Services Agreement with Equinox Research Consulting International (ERCI) for Windjammer Vicinity work
Presentation
Video
May 7 – Approval of Professional Services Agreement with Fullterton & Associates for Property Acquisition
Agenda Bill
Video
March 19 – Contract Amendment #6 with Carollo Engineers for Preliminary Design
Presentation
Video
March 19 – City Council Authorized Submittal of Facilities Plan to Department of Ecology (DOE)
Presentation
Video
Public Meetings
March 6 – Draft Wastewater Facilities Plan was presented, including proposed project phasing and estimated costs.
Presentation (below)
Project Documents
2012
Highlights: City Council selected the Windjammer Vicinity as the new site location.
City Council Agenda Bills
City Council Presentations
November 20 – City Council directed the project team to complete the Facilities Planning process around the Windjammer Vicinity.
Presentation Slides
Presentation Video
Presentation (below)
August 14 – City Council voted unanimously on a resolution to move forward with an MBR plant at the Windjammer Vicinity.
Presentation (below)
July 12 – Results from the June 26-27 Charrette were presented to Council at a Special Council Meeting.
Presentation (below)
April 17 – City Council authorized the technical team to further evaluate two locations for consideration as part of the wastewater treatment facility planning process: Windjammer Park vicinity and Crescent Harbor North vicinity.
Presentation (below)
Public Meetings
July 31 – Meeting provided information about the two sites under consideration for the new wastewater treatment plant.
Comments
Presentation (below)
April 11 – The public meeting covered considered sites and allowed citizens to provide feedback.
Summary
Presentation (below)
Project Updates
The City added an additional site to those being considered for a new wastewater treatment facility.
Map
2011
Highlights: Potential site list was narrowed from eleven to three sites; Community members participated in an online survey about the project.
City Council Agenda Bills
City Council Presentations
November 28 – Clean Water Facility Planning Team requested direction to complete further evaluations of three potential wastewater treatment plant sites.
Presentation (below)
July 27 – Clean Water Facility Planning Team presented information on the five locations under consideration for the new facility.
Presentation (below)
March 9 – Presentation refined and narrowed options for the new facility site.
Presentation (below)
January 13 – Presentation focused on the eleven sites under consideration for the new treatment facility.
Presentation (below)
Public Meetings
Project Documents
December 22 – Report includes responses to questions raised by City Council on November 28.
Project Report
September 16 – Report includes the Clean Water Facility Planning team’s recommendations for location and technology alternatives.
Project Report
May 2 – Community members completed an online survey on the project website in April regarding project awareness, ideas for site improvement, and what qualities were desirable in a new site location.
Community Feedback Report
2010
Highlights: Residents were interviewed about Oak Harbor’s wastewater treatment system; the first public meeting was held.
City Council Agenda Bills
August 4 – Professional Services Agreement with Carollo Engineers
Agenda Bill
March 23 – Selected Carollo Engineers
Agenda Bill
Public Meetings
December 6 – Gathered input on potential locations, the facility siting decision making process, and the factors used to select an alternative.
Presentation (below)
Project Documents
Resident interviews were conducted in fall 2010 to gauge awareness of Oak Harbor’s wastewater treatment system and anticipate questions and concerns in advance of the first public meeting.
Interview Recap